By the end of this task, you will be able to turn a flat list of promises into a sequenced tracker with owners, dates and dependencies — one that keeps running while you are away.
Your situation
You have a register. A register is not a plan. It tells you what was promised; it does not tell you what has to happen first, or what happens on the Monday you are not there.
The recovery runs ninety days. One date inside it is immovable: findings to the customer on 30 April. Everything else works back from that.
Nestor Wilke asked for weekly numbers, not a report at the end. That is a rhythm, not a task, and it has to be in the tracker as one repeating block rather than thirteen copies of the same row.
Important
Deliverable: a ninety-day tracker with owners, dates, phases and dependencies, plus the email that hands it to the three people on it.
Files you'll use
| File | What's in it |
|---|---|
| Your commitment register from Task 1 | What is being tracked |
| CanadaPost_Review_Meeting_Transcript.md | The three phases, and the fixed date |
| CanadaPost_Ops_Network_Findings.md | What the remediation work actually is |
How to read the prompts
Each prompt below is one block you can copy whole. The # lines are labels, not instructions — they mark where the prompt stops setting the goal and starts giving the context, the sources, and the expectations. Copying them along with the prompt does no harm.
Those four moves, in that order, are what makes a prompt work. Use the same shape when you write your own.
Steps
Open Excel and reference your commitment register.
Build the tracker.
Prompt o2-a goalTurn these commitments into a ninety-day action tracker.
contextThe recovery runs from the middle of March to the middle of June, with findings due to the customer on 30 April.
sourcesMy operations commitment list.
expectationsOne row per action, with the owner, the start, the due date, and the commitment it comes from. Group the rows into the three phases the transcript describes rather than inventing your own.
Find what cannot run in parallel. A flat list always looks achievable.
Prompt o2-b goalTell me which of these actions depend on another one finishing first.
contextI have built the list flat and I know at least some of it cannot run in parallel. Findings on 30 April is the fixed point everything works back from.
sourcesThe tracker as it stands.
expectationsList each dependency as one sentence saying which action waits on which, and why. Then name the two actions that most put 30 April at risk if they slip.
Add the weekly rhythm, and make it survive your absence.
Prompt o2-c goalAdd the weekly rhythm to this tracker.
contextThe customer was promised weekly numbers, not a report at the end. Whatever I build has to survive me being away for a week.
sourcesThe tracker.
expectationsSay what has to happen every week, who does it if I am not there, and what the deadline is inside each week. Keep it to one repeating block, not thirteen separate ones.
Move to Outlook and hand it over.
Prompt o2-d goalDraft the email that sends this tracker to the people on it.
contextRecipients are the depot manager, the regional operations director, and the sales manager. Two of them have never seen this tracker and one of them made the promises that created it.
sourcesThe tracker.
expectationsUnder 150 words. Say what the tracker is, what each person owns, what the first deadline is, and where the file lives. One ask at the end, not three.
Save the tracker somewhere the other three can open it. A tracker only you can see is a private to-do list.
Check your work
- Every row has an owner who is a person, not a team.
- Every row traces back to a commitment in the register.
- The dependencies on 30 April are named.
- The weekly block says who runs it when you are away.
- The email asks for one thing.
Stretch prompts
Starting out — get the rows:
Turn this list of commitments into a table with one row per
action, an owner, a start date and a due date.
Comfortable — pressure-test the dates:
Assume the findings date of 30 April cannot move. Work backwards
and tell me the latest date each preceding action can start.
Flag anything that should already have begun.
Confident — plan for it going wrong:
For the two actions most likely to slip, write the one-line
contingency and the trigger that tells me to use it. Say who
decides, and what I tell the customer if it happens.
Tip
The habit here is building for the person covering for you. A tracker that only makes sense to its author fails the first week its author is off, which on a ninety-day recovery is a near certainty.